1/ Becamex Binh Phuoc Power Joint Stock Company is the electricity provider within the Becamex Binh Phuoc Industrial Park.
2/ They offer comprehensive electrical services within the industrial park at reasonable costs, including:
- Consultation for design and supervision of electrical construction projects.
- Implementation of medium and low voltage power supply within customer factories.
- Operation of electrical facilities within customer factories
- Consultation, design, supervision, installation, and business of solar power within the industrial park.
- Preparation of technical agreement documents and connection of electrical projects.
- Maintenance, testing, and certification of electrical equipment according to Circular No. 39/2015/TT-BCT.
3/ The process of electricity provision is summarized as follow: A total duration of 9 days
Step 1: Receive documents and provide additional instructions (if necessary), transfer to the Survey Department (within 1 day)
Electricity purchase documents include:
- 1.1 - Electricity purchase request form (KD-01-02: Electricity Purchase Request Form)
- 1.2 - ID/Passport of the legal representative
- 1.3 - Land Use Right Certificate/ Land Lease Agreement/Decision on land allocation
- 1.4 - Enterprise Registration Certificate/Investment Registration Certificate
- 1.5 - Connection registration information (as provided)
- 1.6 - List of equipment power, daily and monthly load curve, monthly electricity consumption chart (KD-01-03: Equipment Registration - Load Curve)
- 1.7 - Forecast of load demand for the next 5 years
Step 2: Survey and plan for power supply plan (within 1 day)
Step 3: Prepare connection agreement documents, including agreement, technical specification standards, customer invitation letter (within 2 days)
Step 4: Coordinate with the customer on connection agreement documents and service contracts provided by BBP JSC (within 1 day)
Step 5: Customer prepares electrical project design documents
BBP JSC provides a complete electrical project design service to the customer under a service contract (up to 30 days, depending on the project scale).
Step 6: Technical agreement on customer's project design documents submission (within 2 days), including:
- Economic and technical report
- Technical documentation of used materials and equipment
- Single-line diagram
- Detailed technical installation drawings
Step 7: Customer implements construction based on the agreed technical design, with BBP JSC as the supervising entity
BBP JSC provides a complete construction service for electrical projects to the customer under a service contract (up to 60 days, depending on the project scale).
Step 8: Finalize power supply, sign electricity purchase contract upon acceptance of customer's project completion (within 2 days)
Step 9: Execute the electricity purchase contract
Note: If the customer entrusts the entire electrical project to BBP JSC, completion will occur within a maximum of 100 days.